The following points regarding cable laying require attention.

Leave a message

To comply with regulatory requirements, the overall layout design incorporates separate cable channels on the left and right sides; this facilitates the segregated routing of dual-circuit power supply cables, as well as the separation of communication and power cables during installation.

 

During the production design phase, cable routing and specific connection points are determined. Cable tray and penetration fill factors are managed to ensure compliance, and double-layer power cable installation is permitted (with a total cable stack thickness of approximately 75mm).

 

Redundant routing is required for PAGA systems and A/B-channel public address systems. Start points for fire and gas detection loops must be routed separately and kept as far apart as possible-both horizontally and vertically. Power cables and communication cables must be routed separately (with a 50mm clearance), while VFD cables must be routed independently, maintaining a 300mm separation from control and communication cables.

 

High-voltage cables must be routed on cable trays and separated from all other cables by a distance of 300mm. "High Voltage" warning tags must be installed at intervals of no more than 20 meters along the cable run to ensure visibility from any location.

 

As offshore projects operate in harsh environments-subject to extreme temperatures, corrosive gases, and other factors-stainless steel materials are required for cable trays and fasteners located outdoors or near mud pits. Continuous cable trays and independent grounding are mandatory, and MCT cable modules are primarily used for watertight and fire-rated bulkheads.